- Intro
- Conference update
- Release updates
- 1.4.5 was cut
- Make sure it fast syncs first
- Discussion about RC release processDiscussed remainer of 1.4.x releases
- 1.4.6 will be cut this week
- RC this week, reelease week after
- 3-4 Jun
- (release policy)
- 1.4.7 release is cut because 1.4.5 took 3 weeks
- 1.5.0 RC cut in about 2.5 weeks.
- any RC re-spin will be followed by 5 days of sycing
- may impact release of 1.5.0
- 1.4.5 was cut
- Work Updates
- ETC Phoenix
- ETH Berlin
- Went over Ethereum Cat Herders Spreadsheet
- Everything is still in limbo, but that's where we were at for Istanbul at this point too,